Lake Project
July 31, 2009
Friends,
Well, we are on the final phase in construction of the reservoir. We are
encouraged that maybe we may have been able to recoup some of the losses we have
experienced with our investments @ BBT before anymore money needs to go out.
Also, we did not want to interrupt the camps in progress with construction
activity. The last few days we have begun the dewatering process at the dam
site. (a hole down to solid rock, with a pump) With a little help from
mother nature, we hope to be able to remove enough water so that we can attain
adequate compaction for the core of the dam which has to be 97-98%.
Wish us luck! Mother nature has not been very helpful in getting the area dried
out such that we can attain the proper conditions to finish the construction
without a great deal more effort. If we can complete the project and demonstrate
the reservoir is meeting the requirements for which it was built by Oct. 31, we
can make application to the water court to make to make this contingent portion
of our water decree absolute. If we can not make it by the Oct. 31, we will have
to apply for an extension. Other than the application fee and some brain major
damage on our part, an extension to complete the project will not be a problem.
George Over and Roy Grosbach have been incredible in helping us through the more
difficult times and decisions that have had to be made. At the moment, Rosy &
Darrel are being a tremendous help by monitoring the pumping in the dewatering
process.
Construction has not been without its challenges. In the photo, the flagged
string shows the water level at the dam. We should end up with two volleyball
courts and some additional leveler area below the campfire ring.
Sincerely,
Howard & Jan Duncan
Here are a few pictures Howard has taken during the process. Click on the pictures to see a bigger image.